See Chapter 11 in the PMBOK ® Guide.
Project
Management, A Systems Approach to Planning, Scheduling, and Controlling,
Seventh Edition by Harold Kerzner, PHD. See Risk in the index.
Kepner-Tregoe’s
work on Problem Analysis, Potential Problem Analysis and Decision
Analysis, etc. See their web site at www.kepner-tregoe.com.
The
WBS on Page 128 of the PMBOK ® Guide has changed dramatically
from the previous edition and is now as follows:
1. Risk
Management Planning
2. Risk Identification
3. Qualitative Risk Analysis
4. Quantitative Risk Analysis
5. Risk Response Planning
6. Risk Monitoring and Control
Comments:
We have
always admired the entrepreneurial, risk taking approach in the
PMBOK ® Guide. The second sentence on page 127 states “It
includes maximizing the probability and consequences of positive
events and minimizing the consequences of adverse events to project
objectives.”
Projects
are inherently risky because they are unique. If you don’t
like risk, don’t do projects. Your boss has to remember that
the person who never made a mistake, never made anything! "Management
by Exception" (MBE) discussed above, only works if there is
sufficient trust in the organization to concentrate on the things
that went wrong and how they will be fixed. We have seen first hand
the dramatic difference that MBE can make. Companies that adopt
it generally have great morale, team spirit and productivity, less
bureaucracy and thinner reports, successful projects, etc. It is
very difficult to change a culture that unduly punishes honest mistakes.
It may be better to leave and find a company with more potential.
You
can easily customize Microsoft Project to do much of the arithmetic
on pages 136 and 137 of the PMBOK ® Guide for you. E.g. you
use one of the Number fields to put in the Impacts for each activity.
We generally just put in Moderate 0.2, High 0.4 and Very High 0.8.
Use the next Number field to enter Probability. We generally just
enter 0.5, 0.7 or 0.9. Use a third number field to calculate the
product or Risk Score e.g. 0.8 Impact * 0.9 Probability gives a
Risk Score of 0.72 shown in the top right hand corner on Fig 11-3.
We can then use the Microsoft Project filters to find just the activities
with Total Float less than 5 days and Risk Score greater than 0.18.
The software can also turn on a colored flag to highlight risky
activities.
Decision
Tree Analysis as shown in Figure 11-6 can be great for brain storming.
“Solving the decision tree indicates which decision yields
the greatest expected value … when all the uncertain implications,
costs, rewards, and subsequent decisions are quantified.”
Don’t take these solutions at face value though. Look for
solutions that can make a huge difference to the expected value.
In the
example, the cost of building a new plant is $120 (million?) vs.
$50 to upgrade the existing plant. If there is a strong product
demand, the payoff will be $200 for a new plant vs. $120 for the
upgraded plant. If there is a weak product demand, the payoff will
be $90 for a new plant vs. $60 for the upgraded plant. At face value,
the pay offs are as shown in Scenario A and you should choose to
upgrade the existing plant. However, note the sensitivity of the
calculation. If it costs $70 to upgrade the existing plant instead
of $50 the decision is reversed as shown in Scenario B below. It
is so easy to look at different scenarios in project management
or spread sheet software.
| Decision |
Cost |
Payoff |
Payoff
- Cost |
Prob |
Product |
Net
Path Value |
| SCENARIO
A |
|
|
|
|
|
|
| Build
New Plant |
120
|
200
|
80
|
0.65
|
52
|
|
| Upgrade
Existing Plant |
50
|
120
|
70 |
0.65 |
45.5 |
|
| |
50
|
60
|
10
|
0.35
|
3.5
|
49 |
| |
|
|
|
|
|
Choose |
| SCENARIO
B |
|
|
|
|
|
|
| Build
New Plant |
120
|
200 |
80 |
0.65
|
52
|
|
| |
120 |
90 |
-30 |
0.35 |
-10.5 |
41.5 |
| |
|
|
|
|
|
Choose |
| Upgrade
Existing Plant |
70
|
120
|
50
|
0.65
|
32.5 |
|
| |
70
|
60
|
-10
|
0.35
|
-3.5
|
29 |
| |
|
|
|
|
|
Choose |
We became great believers in Kepner Tregoe’s Potential Problem
Analysis years ago when a brain storming session revealed a risk
that could be avoided for a cost of $7,000. This decision saved
us $3 million a few weeks later.
Litigation
has become a huge risk in the USA for many industries e.g. construction
in public agency work. See our comments on Mediation under Claims
Resolution support.
The
PMBOK ® Guide talks about Avoidance, Transference, Mitigation
and Acceptance on pages 142 and 143.
One
example of transference is to contract the work to others which
is covered in the following Project Procurement Management Chapter.
|